Timeline
2024
Q1 2024
Community Engagement and Awareness
Q2 2024
Public Open House Education Events
Submit Special Exemption Permit
Submit Interconnection Request
Q3 2024
Environmental Site Assessment
Geotechnical Field Testing
Q4 2024
Interconnection Agreement Approved
2025+
Q2 2025
Federal, State and other Local Permits Approved
Q3 2025
Start of Contruction
Q3 2027
Commercial Date of Operation
2062
Project Repower or Decommissioning